Holborn Station Machine Chambers 1 to 3 – Cleaning & Decorating Works

Project: Holborn Station Machine Chambers 1 to 3 – Cleaning & Decorating Works Client: LUL – L&E Team Works Value: £66,000.00   Following the refurbishment of the escalators by LUL we were given an order for comprehensive cleaning and repainting of the Machine Chambers. During the cleaning and painting works we protected LUL assets at all […]

Stratford Market Depot Security Works – Installation of New Air Conditioning Unit in Security Suite

Project: Stratford Market Depot Security Works Installation of New Air Conditioning Unit Client: Tube Lines Limited Works Value: £9,542.00   Due to change of use D&D Rail were instructed to install a new Air Conditioning Unit in a room in the Security Suite at Stratford Market Depot.  The scope was to install a unit to same […]

Canning Town Station – Removal of Platform Supports

Project: Canning Town Station – Removal of Platform Supports Client: Tube Lines Limited Works Value: £10,500   There were 12 outriggers in total, 6 along each platform located some 14.5m apart.  Each was formed of a single spine beam with 10 side spur members and 22 tie bars. Due to the arrangement of the outriggers, access […]

Chancery Lane Station – Civil & Premises Works

Project: Chancery Lane Station Civil & Premises Works Client: London Underground Limited – L&E Works Value: £525,000   Escalators 1&3 at Chancery Lane Station required replacing under the L&E Framework.  DDR were contracted with both the civil & premises aspects of the project, and works were carried out over three phases and three Station Closures […]

Upminster Depot – FIRAS Works

Project: Upminster Depot FIRAS Works Client: LUL SWIP Works Value: £110,000   There is a new building at Upminster Depot ‘Ancillary Building’ that was built by others.  The services of DDR were employed to install 5No new double glazed window units, strengthen existing apertures and install 9No new steel door sets (2No of these installed […]

Watford Station – FIRAS Works

Project: Watford FIRAS Works Client: Orion Engineering for LU Fire Team Works Value: £13,600   There are two new rooms located at Watford Station (SER & ESR) that were built by others.  The LUL Fire Team employed the services of DDR to maintain a one hour fire compartment with passive fire protection works under our […]

Kilburn Station – Roof Works

Project: Kilburn Station – Roofing Works Client: Tube Lines Limited Works Value: £70,000   The existing rendered walls to Upper & Lower Roof Areas required attention due to water ingress into the Station Entrance below.  As part of our framework for Minor & intermediate Works we were required to clean off the existing debris, scrape off […]

Manor House – Drainage Works

Project: Manor House Station – Drainage Works Client: Tube Lines Limited Works Value: £7,000   As part of our framework for Minor & intermediate Works we were required to fabricate and replace the existing stair drainage channel gratings on Exits 1- 5 & 7.  This also included cleaning out all drainage channels and gratings on each […]

Mill Hill East – Platform Replacement

Project: Mill Hill East Station – Platform Replacement Client: Tube Lines Limited Works Value: £150,000   Works at this station comprised of the replacement of the existing platform decking/ surfacing and defective structural timber members beneath the platform.  In addition to this we are to remove the lead based paint from the lighting standard support steelwork. […]

Edgware Depot – Kitchen

Project: Edgware Depot – Kitchen Client: Tube Lines Limited Works Value: £7,000   These works consisted of the supply and installation of a small kitchen in the Security Hut at the entrance to Edgware Depot. In addition to this we relocated and fixed an Armco Barrier around the perimeter of a new car parking area, broke […]

Whitechapel Station – Roofing Works

Project: Whitechapel Station – Roofing Works Client: London Underground Limited Works Value: £75,000   As part of the works to install a new SER at Whitechapel Station there was a requirement to further waterproof the roof slab due to water ingress.  The initial works were carried out during a 72 hour Possession with the remainder on […]

Wembley Park Station – FIRAS Works

Project: Wembley Park Station FIRAS Works Client: SSE Value: £14,000   There are two new rooms located at Wembley Park Station (SER & ESR) that were built by others.  The LUL Fire Team employed the services of DDR to bring the room up to a one hour fire compartment with passive fire protection works under […]

South Harrow Station – REB Base

Project: South Harrow Station – REB Base Client: Tube Lines Limited Value: £18,000 As part of our framework for Minor & intermediate Works we were required to form a hard standing concrete base to accommodate an REB unit for the local signalling interface replacement works for APJNP. We were also required to use a crane […]

Neasden Depot – FIRAS Works

Project: Neasden Depot – FIRAS Works Client: Orion Engineering on behalf of SSE Plc Works Value: £7,500   There are two new rooms located at Neasden Depot (SER & ESR) that were built by others.  The LUL Fire Team produced a ‘Condition Report’ to bring the room up to a one hour fire compartment, and DDR […]

Kingsbury Station – Re-bedding Tactiles

Project: Kingsbury Station – Re-bedding Tactiles Client: Tube Lines Limited Works Value: £72,000 The majority of the tactiles on Platforms 1 & 2 at Kingsbury Station were found to be loose and uneven.  The joint between the tactiles and the platform nosings was also found to have fragmented over time.  Our scope was to remove all of […]