C01: – Civils Package Works

Project: C01 – Fluor Connect Enabling Works

Client: Fluor Limited

Value: Overall Project £13 Million

 
New trackside cable containment, together with installation of 75 kilometres of new cable, new trackside equipment bases and formation/upgrade of new rooms within station environments. Climate control to various CER’s.

  • Enabling works for the CO1 ring. This work includes the installation of concrete bases and amplifier frames and associated pull out tests. Alarm and power cables are then pulled to these frames from the station.

 

 