Moorgate Station: – Construction of New SER Room

Project: Moorgate Station – Construction of New SER Room

Client: Tube Lines Limited

Works Value: £113,000

 
Construction of a new SER room within an existing lift shaft at Moorgate Station.  The new SER was to be built 3 metres up the shaft, supported on a steel superstructure. Our works on this project commenced as follows, once the Holorib deck had been installed by others:

  • Infilling of tunnel pans with C40, around the shaft perimeter.
  • Installation of the rebar into the Holorib floor slab.
  • Pouring the concrete for the floor slab – 400 bags of C40 mixed on site.
  • Building of the blockwork walls to soffit height, incorporating wind posts.
  • Installation of concrete lintels between blockwork piers to support roof slab Holorib.
  • Installation of rebar and pouring concrete roof slab – 400 bags of C40 mixed on site.
  • Fire cladding of wind posts, new beams and existing steel columns.
  • Screeding of new SER floor and roof slab to a fall.
  • Decoration of walls and floor.
  • Installation of roof edge trim and guttering with down pipe.
  • Waterproofing to the roof area. Includes Vandex BB75 and stainless steel apron.

 

 